A bipartisan group of ten Arkansas state senators has filed a bill to fully repeal the Generating Arkansas Jobs Act, or GAJA, the 2025 law that lets electric utilities charge ratepayers for the cost of building new power plants before those plants are up and running.
Senate Bill 2 was filed Monday, Nov. 16 — the first day lawmakers could file bills for the 2027 legislative session — by Sen. Clint Penzo, a Springdale Republican and the Senate majority whip. Eight Republicans and two Democrats signed on as sponsors.
The bill would repeal GAJA, including its provisions for the “strategic investment rider” that lets utilities recover construction costs through an extra charge on customers’ bills. The 2027 session begins Jan. 11, and the bill will be considered then.
What GAJA does
Passed as Act 373 of 2025 and signed by Gov. Sarah Huckabee Sanders, GAJA changed how Arkansas utilities can recover the costs of building new power generation. Instead of waiting until a plant is finished and producing electricity, utilities can start collecting construction costs from ratepayers while the plant is still being built, through the strategic investment rider.
Supporters of the law said it was needed to attract data centers and other large businesses that need reliable power, and that it protects ratepayers from sudden, steep bill increases by letting utilities add construction costs to bills gradually over time.
Critics say the law has done the opposite — shifting the cost and the risk of big construction projects onto customers before they get any electricity from them — and they blame it for higher electric bills. Entergy Arkansas has already raised monthly bills by about $5.77 under the law, according to reporting by The Arkadelphian.
Who is behind the repeal
Besides Penzo, the bill’s sponsors are Republican Sens. Ronald Caldwell of Wynne, Terry Rice of Waldron, Ricky Hill of Cabot, Jimmy Hickey, Missy Irvin of Mountain View, Mark Johnson of Ferndale, and Bryan King of Green Forest. The Democratic cosponsors are Sen. Jamie Scott of North Little Rock and Sen.-elect Tara Shephard of Little Rock. The bill lists no House cosponsors.
Some lawmakers who voted for GAJA in 2025 have since said they regret it. Sen. Steve Crowell has publicly described his vote for the law as a mistake, and Hickey, now a cosponsor of the repeal, has also expressed regret over supporting the original law, according to the Arkansas Advanced Energy Association.
GAJA’s main sponsor in 2025 was former Sen. Jonathan Dismang of Searcy, who resigned his seat this year to take a job as vice president of external affairs for Arkansas Electric Cooperatives.
The bill would also make related changes to Arkansas utility law, including a provision that would bar a generation and transmission cooperative from increasing its rates and charges by more than 8% in total during any 24-month period.
What happens next
Filing the bill does not change anyone’s electric bill. SB2 still has to pass the Senate and the House and be signed by the governor before it would take effect, and questions remain about how a repeal would affect projects and riders already approved under the law.
The governor’s office has not said whether Sanders supports the repeal, and utility companies said they were reviewing the proposal. Strong opposition from utilities and a robust debate are expected when the session opens in January.
For Texarkana-area households, the fight is worth watching: whatever lawmakers decide about construction-period charges will shape how Arkansas utilities pay for new power plants — and how much of that cost shows up on customers’ bills before the plants ever produce a watt.
Sources: Arkansas General Assembly, Senate Bill 2; The Arkadelphian; Arkansas Advanced Energy Association; The StatePageAR.